26-05-2022

Construction works annex
Carpentry work: Drawers for the 1st house completed (to be installed on Friday); doors of the 2nd house to start next week. Paint work to start Saturday (exterior colour to choose on site). Missing tiles are in production and will be delivered next week. Kitchen marbles, exterior pavement and aluminium windows next week. Meeting on site May 27th with Sr.Salvador, Sr. António, Célia.

Planning Submission - Cottages
Two different planning submissions are to be made. All drawings completed and A+ is working on the written documents. To be submitted in the 1st week of June. Meeting with Arch. Ivânia for project review on June 1st. Plans for the review of the area registry were sent to Luís Rosado.

Tender - Pool House
Tender reviewed and sent to quote.

26-05-2022

Construction works annex
Carpentry work: Drawers for the 1st house completed (to be installed on Friday); doors of the 2nd house to start next week. Paint work to start Saturday (exterior colour to choose on site). Missing tiles are in production and will be delivered next week. Kitchen marbles, exterior pavement and aluminium windows next week. Meeting on site May 27th with Sr.Salvador, Sr. António, Célia.

Planning Submission - Cottages
Two different planning submissions are to be made. All drawings completed and A+ is working on the written documents. To be submitted in the 1st week of June. Meeting with Arch. Ivânia for project review on June 1st. Plans for the review of the area registry were sent to Luís Rosado.

Tender - Pool House
Tender reviewed and sent to quote.